I've been going to the Regional Foundations Library for help with my fundraising for this project. Allison has been holding my hand through the whole process. She told me to make a "road map" which is basically a schedule or a rough outline of where I'm going with this project. Here's what I got so far:






PRE-PRODUCTION                                                                                                        5 MONTHS           
DECEMBER            2010                        CONTACT MAGDA SAYEG
JANUARY               2011                        CONTACT ADDITIONAL SUBJECTS
                                                             ASSEMBLE CREW
                                                             RESEARCH GRANTS AND SPONSORS 
APRIL                     2011                        LAUNCH INDIEGOGO CAMPAIGN (120 DAYS)
JUNE                      2011                        SUBMIT TFPF APPLICATION
                                                             SUBMIT CINEREACH APPLICATION
JULY                      2011                        FUNDRAISER EVENT
                                                             SUBMIT ITVS APPLICATION
JULY 31                  2011                        FINISH INDIEGOGO CAMPAIGN           
AUGUST                 2011                        FINAL FUNDRAING EFFORTS           

PRODUCTION                                                                                                                                  1 YEAR           
FEBRUARY            2011                        SHOOT AND EDIT SXSW BUMBER
                                                             SHOOT B ROLL OF KNITTING GROUPS
MARCH                  2011                        SHOOT KNITTED WONDERLAND PROJECT, Austin TX (3 DAYS)
                                                             INTERVIEW MAGDA SAYEG
JUNE 11                2011                         INTERNATIONAL YARN BOMBING DAY SHOOT
AUGUST                2011                        SHOOT “YARN BOMBERS” IN VANCOUVER (6 DAYS)
                                                             FILM IN SEATTLE (2 DAYS)                                   
SEPTEMBER         2011                        SHOOT  “ LANDSCAPE” IN NETHERLANDS (6 DAYS)
OCTOBER             2011                         SHOOT  “INCOGKNITO” IN LONDON (4 DAYS)
                                                             SHOOT  “MICROFIBER MILITIA” IN LONDON (4 DAYS)
NOVEMBER          2011                          SHOOT  “MASQUERADE” IN STOCKHOLM (6 DAYS)
DECEMBER          2011                          SHOOT  CHRISTMAS EXHIBITS IN AUSTIN (2 DAYS)           
JAN-MARCH          2012                        CONTINUE LOG FOOTAGE
                                                                ADDITIONAL FUNDAISING EFFORTS
APRIL                   2012                       SHOOT  “LFS” IN DENVER (5 DAYS)
                                                                SHOOT   “MILITIA” IN CHICAGO (5 DAYS)           
MAY                      2012                       LOG FOOTAGE
JUNE 11,               2012                        INTERNATIONAL YARN BOMBING DAY (1 DAY)
SUMMER              2012                        ADDITIONAL PRODUCTION (TBA)
                                                               RAISE FINISHING COSTS
                                                               BEGIN ASSEMBLY CUT

POST-PRODUCTION                                                                                                      10 MONTHS           
FEBRUARY-DECEMBER    2011                       LOG AND CAPTURE FOOTAGE
JANUARY-AUGUST           2012                       CONTINUE LOG AND CAPTURE FOOTAGE
SEPTEMBER                    2012                        BEGIN ROUGH CUT
DECEMBER                      2012                        FINISH ROUGH CUT
JANUARY                         2013                        BEGIN FINE CUT
MARCH                            2013                        FINISH FINE CUT
                                                                          PRELIMINARY TITLE WORK
APRIL                              2013                        LOCK PICTURE
                                                                          FINISH TITLES
MAY                                2013                        COLOR CORRECTION
                                                                          SOUND MIX

DISTRIBUTION                                                                                                             5 MONTHS           
JUNE                              2013                DVD AUTHORING/PRINTING
                                                              PRIMARY FESTIVAL SUBMISSIONS
SUMMER                        2013                SCREENING FOR DISTRIBUTERS
                                                              COMMUNITY SCREENING
FALL                               2013               FILM FESTIVALS
SPRING                          2014               FILM FESTIVALS